Due to its continued growth, the organization needed additional space
-
A storage and space solution that increased capacity to match the organization’s growing inventory was needed
-
The solution needed to consider the safety of both employees and the building’s contents
- Reviewed the existing design and suggested improvements to create a more customized design
- Discovered that the heating installation (gas lines) would interfere with future storage installations, causing a loss of valuable storage space
- Worked with staff to create a racking solution that would increase capacity
- Installed blue, custom-colored pallet racking
- Worked out pallet rack to improve from 10 bays per row to 12 per row and standardized the height.
- Moved and repurposed spool cable racking from the organization’s other facility
- Increased safety in the facility by adding rack guarding
- Increased storage capacity by 29% due to suggested improvements including the relocation of structural elements
- Working smoothly with multiple contractors to finish on-time and within budget
Client Testimonial
“Working with Kraftwerks on our building 12 installation was smooth and efficient. Kraftwerks provided excellent support, addressing all details and adjustments promptly. The professional crew completed the job on time, and any issues were resolved quickly. Highly recommend!”